The site
This office building in Waterbury, CT has two very different parking areas. Some spaces sit directly alongside the building, while most of the parking is located toward the rear.
The challenge
Ownership wanted charging available close to the building, but they also did not want to ignore the larger parking area in the back.
How we solved it
Instead of forcing the entire EV charging setup into one location, our team designed around both needs, creating two separate charging sites so drivers can charge where they already park.
Good EV infrastructure is not just about finding somewhere to put a charger. It is about understanding how the property actually works.
Sometimes the best layout is not the simplest one. It is the one that fits the property. That is what Poweral carries from start to finish, so the site just works.
Originally shared on LinkedIn as part of The Current, Week 14. View the post on LinkedIn.
More from The Current
Reusing Idle Fast-Charger Power for 8 Level 2 Chargers at a Foxborough, MA Hotel
With no spare electrical capacity, we put the power from out-of-use DC fast chargers to work for the hotel's new Level 2 chargers.
Read the storyHandling Contaminated Soil During an EV Charger Installation in Washington, NJ
Soil along the trench route turned out to be contaminated. We brought in a specialized environmental company and kept the project moving.
Read the storyHelping Drivers Find the Chargers in a 1,500-Space Lot in Paramus, NJ
With parking wrapped around both sides of a large office building, wayfinding was the whole challenge.
Read the story